Velocity Air Hangers Partial Demolition

Related Document: Velocity.png

 

   

                                                  Tucson International Airport

 

RE:   10213464 Velocity Air Hangars Partial Demolition

Project begins on Friday March 14, 2014

Duration:  Four weeks

WORK CONSISTS OF:

  • Installation of a temporary fence in compliance with the measures established by the Airport Security Program Temporary Amendment
  • Removal of hangar bays 4 - 8
  • Installation of a permanent fence
  • Roof repair on hangar bays 1 - 3

 

See attached diagram.   

Please use Extreme Caution while in the construction area.

 
                     