RE:        10106429 Main Terminal Apron Reconstruction

Construction will begin on Work Zone 10 on Saturday January 11, 2014.

WORK CONSISTS OF: 

  • Obliteration and temporary re-striping of taxilane and service road markings

on the terminal ramp east of Concourse A

  • Demolition of concrete ramp

 

SCHEDULE AS FOLLOWS:

OLBLITERATION AND RE-STRIPING

Saturday January 11, 2014 through Sunday January 12, 2014

DEMOLITION

Monday January 13, 2014 through Friday January 24, 2014

TAA Personnel will coordinate the activities with each airline operations as the work progresses.  Access to east baggage will remain open.  Construction access will be through temporary SIDA Gate SA4.

See attached diagram.   

Please use Extreme Caution while in the construction area.

PRIMARY PROJECT CONTACT:

 

Routine Project Information:               Mark Staszak (520-573-8014)

Construction Emergencies (24/7):        Mark Staszak (520-573-8014) OR

Page Via TAA Communications Center (520-573-8182 or 8111)